Construction of 4 New 132/33kV Substation at Khagrachari, Rangamati, Bianibazar & Sunamganj and Renovation of 6 Nos. 132/33kV S/S at Chandraghona, Narshingdi, B.Baria, Mymensingh Tangail & Chattak under 10 substation project of PGCB in conjunction with ABB Ltd. India.

Year Of Completion

Dec’19

Construction Erection and commissioning of 400/230kV Substation at Bhulta in conjunction with ABB Ltd. India.

Year Of Completion

July’19

Construction of 230kV Switching Station at Bibiyana in conjunction with ABB.

Year Of Completion

Oct’17

Construction of 230kV New Substation at Fenchuganj & Extension of 230kV Comilla(N) & existing 132kV Fenchuganj Substations in conjunction with ABB.

Year Of Completion

Nov’2013

Civil & Erection works incl. Inland Transportation and Testing & Commissioning for Construction of 132/33kV Gas Insulated Switchgear (GIS) Substation at Gallamari with Associated T/L & Extension of Existing 230/132kV Khulna South Substation.

Year Of Completion

Feb’13

Renovation & upgradation of Shyampur, Maniknagar & Moghbazar 132/33kV Substation in connection with ABB,India.

Year Of Completion

Sept’2011

Extension including installation of 75MVA Transformer at Rampura, Haripur and Aminbazar 230/132kV Substation in conjunction with SIEMENS India.

Year Of Completion

Oct’09

Extension of Rehabilitation of 7 numbers 132/33kV and 21 numbers 33/11kV substations at Chittagong in conjunction with CCC, china under 28 S/S project.

Year Of Completion

Sept’09

Construction, Erection and Commissioning of 4 Numbers of 132kV and 6 Numbers of 33kV Substations under Greater Dhaka Power Project Phase-IV, in conjunction with CCC,China.

Year Of Completion

June’09

Construction, Erection and Commissioning of 230/132kV Substation at Bogra in conjunction with ABB,Germany.

Year Of Completion

Nov’2008

Civil and Erection works for ‘RPC’ Reactive Power Compensation Project at 5 Substations in an around Chittagong in conjunction with M/S.CCC, China.

Year Of Completion

Jan’2008

Construction, Erection & commissioning of 230kV S/S at Serajganj and extension of 230kV substation at Ashuganj in conjunction with ABB, India.

Year Of Completion

Sept’07

Construction incl. Erection and commissioning of 230kV substation at Barapukuria incl. extension of existing Rangpur & Saidpur 132kV substation in conjunction with ABB, Sweden.

Year Of Completion

Dec’06

Construction, Erection & commissioning of 132/33kV substation at Satkhira.

Year Of Completion

Nov’06

Extension incl. commissioning of 230kV Tongi & and 132kV Tongi & Kallyanpur substation in conjunction with SIEMENS Ltd. India.

Year Of Completion

Sept’05

Construction, Erection & commissioning of 132kV Uttara substation under Greater Dhaka Phase-IV
with GPTC, China.

Year Of Completion

Aug’2005

Construction of new Chandpur 132/33kV and extension of Chowmuhani 132/33kV substation in conjunction with CCC, China.

Year Of Completion

Dec’04

Civil & Erection works of 132/33kV substation at Julda, Shahmirpur & Bakalia in conjunction with CCC, China under Greater Chittagong Phase-III.

Year Of Completion

Aug’04

Erection & commissioning of 5 Nos. 33/11kV substation under 9 Town Power Distribution Project in conjunction with ABB, Norway.

Year Of Completion

Aug’04

Civil & Erection works for incl. commissioning of 34 Grid substations with CCC, China under
RRAGS Project, Phase-III.

Year Of Completion

Oct’03

Extension of one diameter for 230kV Haripur substation and construction of 230kV interconnector between Haripur 360MW Power Plant and Substation.

Year Of Completion

June’03

Construction incl. erection and commissioning of Rampura 230/132kV substation in conjunction with Mahkota Technologies Sdn.Bhd. Malaysia.

Year Of Completion

Dec’02

Extension of 132kV Grid Substation at Faridpur and Madaripur under 16 Grid substation project of BPDB
with Emirates Trading Agency Dubai.

Year Of Completion

March’0

Civil & Erection works incl. commissioning of 34 Grid substation with CCC, China under RRAGS Phase-I

Year Of Completion

Aug’98

Erection & Installation works for extension of 230kV Hathazari substation with CMEC, China.

Year Of Completion

Dec’96

Civil & Erection works of 132/33kV substation under Greater Dhaka Power Project, Phase-IV with Hawker Siddeley Power Engineering Ltd. UK. (Total 35 S/S).

Year Of Completion

June’95

Civil & Erection works of Comilla(North) 230kV substation and extension of existing 230kV Ashuganj & 132kV Comilla(South) substation in conjunction with ABB, Germany.

Year Of Completion

Dec’92

Construction and Erection of 2 New and Extension of 4 existing (Total 6) 132kV Two 33kV substation and construction of Distribution Control Centre under Greater Dhaka Power Project, Phase-II with Hawker Siddeley Power Engineering Ltd. of UK.

Year Of Completion

Dec’88

Construction incl. Erection & Installation of 5 New 33/11kV and extension of 5 existing 33/11kV substation under Greater Dhaka Power Project,
Phase-II with Kanematsu Gosho Ltd. of Japan.

Year Of Completion

June’88

Construction incl. Erection & Installation of Kaptai and Hathazaru 132kV in conjunction with Toyo Menka Kaisha Ltd. Japan.

Year Of Completion

Dec’87

Erection & Installation of two 33/11kV substation ‘Asad Gate’ Dhaka and at Chapainawabganj for BPDB

Year Of Completion

Dec’75